Project 02Deadline-led education project

Tor Bridge High

Custom-coloured doorsets, programmed around the return to school.

  • Education
  • Deadline-led
  • Installation
Custom-coloured orange fire doorset with vision panel and oak frame, Tor Bridge High
Custom-coloured doorset · Tor Bridge High
Sector
Education
Principal contractor
Mercury Construction
Scope
Custom-coloured doorsets
Deadline
Return to school
Situation

Tor Bridge High needed its fire doorsets installed around the school calendar, with the work programmed to finish before students returned.

JFD worked alongside principal contractor Mercury Construction, with doorsets specified in custom colours for the school.

DecideRequirement received

Defined package received through the principal contractor.

The doorset requirement, including the custom colours, came as part of the wider project package.

Deliver

A programme built around the return to school.

The installation had to be sequenced so the building would be ready for students coming back, while sharing the site with Mercury Construction’s wider works.

  1. Work beginsProgramme start
  2. Installation sequenceArea by area
  3. Final checksBefore handover
  4. Students returnStart of term
Mercury Construction site hoarding outside the school building
Shared site · Mercury Construction
Tor Bridge High building signage
Live school site
Outcome

Custom-coloured doorsets delivered alongside Mercury Construction to a return-to-school programme.

A deadline-led education project where the programme mattered as much as the product.

Similar work?

Got a similar piece of fire-door work?

Start with the survey, job sheet, specification or requirement you already have.

Send us your survey or job sheet

Or

Prefer to talk it through first?

Tell us about the building, the doors and the programme.

Talk through your fire-door work →

One site. One backlog.
One defined piece of work.